Can someone give me an explanation of what is going on with the I35 construction between the river and 18th street? I have been recovering from knee surgery and the WV game was my first time to see the extent of the project.
4yrletterbear said:
Can someone give me an explanation of what is going on with the I35 construction between the river and 18th street? I have been recovering from knee surgery and the WV game was my first time to see the extent of the project.
Alf said:4yrletterbear said:
Can someone give me an explanation of what is going on with the I35 construction between the river and 18th street? I have been recovering from knee surgery and the WV game was my first time to see the extent of the project.
Fubar
"Finish"BaylorGuy314 said:
This is one of the final pieces of the overall I-35 expansion plan that's been going on for nearly a decade from Austin to Hillsboro.
As CT said, they are expanding it to 4 main lanes in both directions, adding U-turns, eliminating some old intersections that were traffic problems, etc, etc.
Expected to finish in Spring 2024.
UBBY said:"Finish"BaylorGuy314 said:
This is one of the final pieces of the overall I-35 expansion plan that's been going on for nearly a decade from Austin to Hillsboro.
As CT said, they are expanding it to 4 main lanes in both directions, adding U-turns, eliminating some old intersections that were traffic problems, etc, etc.
Expected to finish in Spring 2024.
You mean get it halfway done and then wait however many years until they can fund the next half and then be done another 5 years after that.
Thats not what I read. I read they will seek funding in 5 years for the second half.BaylorGuy314 said:UBBY said:"Finish"BaylorGuy314 said:
This is one of the final pieces of the overall I-35 expansion plan that's been going on for nearly a decade from Austin to Hillsboro.
As CT said, they are expanding it to 4 main lanes in both directions, adding U-turns, eliminating some old intersections that were traffic problems, etc, etc.
Expected to finish in Spring 2024.
You mean get it halfway done and then wait however many years until they can fund the next half and then be done another 5 years after that.
The whole I-35 expansion is fully funded. It's why it was done in parts.
Perhaps I was unclear. My apologies. Every part of the expansion that is currently under construction is fully funded. The stretch through Waco is the last stretch in the entire project. The numbers are simply far too big when you are spending $50-60MM/mile to do it all at one time. You have to fund it and construct it in pieces.UBBY said:Thats not what I read. I read they will seek funding in 5 years for the second half.BaylorGuy314 said:UBBY said:"Finish"BaylorGuy314 said:
This is one of the final pieces of the overall I-35 expansion plan that's been going on for nearly a decade from Austin to Hillsboro.
As CT said, they are expanding it to 4 main lanes in both directions, adding U-turns, eliminating some old intersections that were traffic problems, etc, etc.
Expected to finish in Spring 2024.
You mean get it halfway done and then wait however many years until they can fund the next half and then be done another 5 years after that.
The whole I-35 expansion is fully funded. It's why it was done in parts.
The southern portion should take less time to complete.southtexasbear said:
I also remember hearing that the reason why they aren't working on the entire Waco stretch (Bellmead to Hwy 6) in one time is that the city of Waco was going to have to pony up a very substantial amount up front as opposed to how it was explained above (in pieces). Waco said gulp and now it's a 10 year process.
How quickly do you think that will get done? They first have to finalize funding. They stated that they also want to give some time off for some of the businesses to try to recover. How much time off does that mean before they start again? It seems more and more like 2030 is when this will finally get finished if not later.BaylorGuy314 said:Perhaps I was unclear. My apologies. Every part of the expansion that is currently under construction is fully funded. The stretch through Waco is the last stretch in the entire project. The numbers are simply far too big when you are spending $50-60MM/mile to do it all at one time. You have to fund it and construct it in pieces.UBBY said:Thats not what I read. I read they will seek funding in 5 years for the second half.BaylorGuy314 said:UBBY said:"Finish"BaylorGuy314 said:
This is one of the final pieces of the overall I-35 expansion plan that's been going on for nearly a decade from Austin to Hillsboro.
As CT said, they are expanding it to 4 main lanes in both directions, adding U-turns, eliminating some old intersections that were traffic problems, etc, etc.
Expected to finish in Spring 2024.
You mean get it halfway done and then wait however many years until they can fund the next half and then be done another 5 years after that.
The whole I-35 expansion is fully funded. It's why it was done in parts.
The only part that is "unfunded" (although it's technically already earmarked) is the 3 mile (or so) stretch from Valley Mills Dr to the Marketplace. It's the last piece to be done from Austin to Hillsboro. But the funding for that piece should be substantially easier - it's half the price of the section from Valley Mills Dr to Behrens Circle (the current part under construction).
CorsicanaBear said:
I see it as a failure (one of many) of our local politicians. Temple managed to get their upgrade funded all in one go, why didn't Waco?
Did they say "hey, do us last" instead of taking the medicine when it was first offered and funds were available, thereby delaying completion by nearly a generation?
CTbruin said:
Expanding to 6/8 lanes from Bellmead to 12th st.
5 year plus project.
The Temple project was much less expensive than the Waco project.CorsicanaBear said:
I see it as a failure (one of many) of our local politicians. Temple managed to get their upgrade funded all in one go, why didn't Waco?
Did they say "hey, do us last" instead of taking the medicine when it was first offered and funds were available, thereby delaying completion by nearly a generation?